Beijing Duowei Group
Mexico Smart Factory Project
Tailored bulk charter solution for Beijing Duowei Group: Safely transport approximately 3000 cubic meters of smart factory production equipment, steel structures, and automated production line components from Qingdao Port, China, to Monterrey, Mexico. Providing end-to-end door-to-door service from port consolidation to final delivery at the factory.
Project Overview
Beijing Multi-Dimension Group plans to build a smart manufacturing plant in Monterrey, Mexico, requiring the shipment of heavy machinery, steel structures, automated production line components, and construction materials from China. Due to the diverse cargo types, varying specifications, and oversized equipment, standard container shipping is insufficient. Our company designed a customized charter for an entire bulk carrier, safely transporting 3000 cubic meters of cargo in one go to ensure the project proceeds on schedule.
The project involves various oversized equipment, including large stamping machines, automated welding robot workstations, and steel structural frames. The heaviest single item exceeds 15 tons, with the longest reaching 12 meters. We must coordinate cargo consolidation from multiple domestic suppliers at the port, manage loading plans, and ensure orderly unloading according to the factory construction sequence upon arrival.
Service Highlights
Charter the entire bulk carrier
Based on total cargo volume and characteristics, we select an optimal LCL vessel for chartering the entire shipment of 3000 cubic meters in one go, avoiding the time risks and added costs associated with split shipments.
Specialized loading for oversized equipment
For oversized cargo such as large stamping machines and 12-meter steel structures, we develop specialized stowage plans and securing measures to ensure zero damage during ocean transit.
Multi-vendor port consolidation
Coordinate cargo consolidation from over 10 domestic suppliers, schedule loading based on factory construction priorities, and unload in sequence upon arrival to minimize on-site wait times.
Full Protection and Insurance
Precision equipment is packed with triple-layer protection against moisture, vibration, and rust. All shipments are covered by ocean cargo insurance, and high-value items are escorted by dedicated personnel.
One-stop door-to-door service
End-to-end service from domestic pickup, port consolidation, customs clearance, ocean freight, Mexico customs clearance, and inland transport to your Monterrey factory—just one point of contact for you.
Precise Time Control
Align with the Mexico factory construction schedule to back-calculate milestones for each stage, enabling end-to-end visibility from port consolidation to factory delivery and ensuring on-time arrival.
Project Data
Shipping Route
From Qingdao Port to Monterrey, Mexico, the journey spans approximately 14,000 nautical miles across the Pacific Ocean.
Qingdao Port
Port consolidation and loading
Consolidate goods from multiple suppliers at Qingdao Port and complete stowage and securing.
Pacific Route
Approximately 25 days of sailing
General cargo ship crosses the Pacific Ocean with real-time tracking throughout the journey.
Port of Manzanillo
Port clearance
Complete customs inspection and clearance procedures efficiently
Monterey Plant
Delivery ready
Heavy flatbed truck delivers to factory; unload and position in sequence.
Project Timeline
From solution planning to factory delivery, the entire process takes approximately 4 months.
Project Initiation and Solution Planning
Coordinate with the Beijing Duowei Group project team to compile the full cargo manifest and dimensional/weight data, conduct on-site equipment parameter inspections, and develop a breakbulk vessel charter plan along with the stowage schedule.
Multi-vendor Port Consolidation
Coordinated with over 10 suppliers across Beijing, Tianjin, Qingdao, Shanghai, and other locations to consolidate shipments in batches at the Qingdao Port yard, completing acceptance, volume measurement, numbering, and warehousing.
Professional Packing & Reinforcement
Stow 3000 cubic meters of cargo according to the loading plan. Secure large equipment with steel cables and wooden supports; equip precision equipment with shockproof and moisture-proof packaging.
Customs declaration and shipment
Export customs clearance completed. The breakbulk vessel departed from Qingdao Port, crossed the Pacific Ocean, and is en route to Manzanillo Port, Mexico. Real-time vessel tracking provided throughout the journey.
Arrival & Customs Clearance
Cargo arrived at Manzanillo Port, Mexico. Coordinated with local customs broker in advance to prepare documents, ensuring efficient customs inspection and release procedures.
Inland Transportation & Delivery
Schedule heavy flatbed trucks to transport equipment from Manzanillo Port to the Monterrey plant site. Unload according to construction priority and complete equipment placement and acceptance.
Project Photos
Actual project photos can replace the images below.

On-site loading of large equipment onto vessels

Bulk carrier loading at Qingdao Port

Steel components staged at port for loading

Device hardening and protection

Offloading at Mexican ports

On-site delivery at the Monterey plant
Project Outcomes
All 3000 cubic meters of cargo safely arrived at the Monterrey factory site in Mexico with 100% equipment integrity. The project's delivery timeline fully met the factory construction schedule, earning high recognition from Beijing Multi-dimensional Group. Both parties have reached a strategic cooperation agreement for logistics support in the upcoming Phase II factory expansion.